Project

General

Profile

Edit Copy Actions

Feature #8751

open

Update client requirement/defect sheet based on previous meetings & split the work to the team

Added by Anonymous about 1 month ago. Updated about 1 month ago.

Status:
New
Priority:
Normal
Target version:
-
Start date:
05/05/2026
Due date:
05/05/2026 (33 days late)
% Done:

100%

Estimated time:
6:00 h

Add

Subtasks


Add

Related issues

Updated by Anonymous about 1 month ago

  • % Done changed from 0 to 100
  • Estimated time changed from 4:00 h to 8:00 h

Assigned tasks to the team & take the updates from them
Attended the client meeting to track all the issues & requirements

Actions #2

Updated by Anonymous about 1 month ago

  • Tracker changed from Support to Feature
Actions #3

Updated by Anonymous about 1 month ago

  • Estimated time changed from 8:00 h to 6:00 h
Edit Copy Actions

Also available in: Atom PDF