Working on E-commerce application to manage team and clarify there doubts on flow and worked on checkout and cart screens related issues and do unit testing to find out issue and discuss with backend team.

Added by Teja Sriram Sangani about 2 months ago. Updated about 2 months ago.

Status:
In Progress
Priority:
Normal
Target version:
-
Start date:
10/21/2025
Due date:
10/24/2025 (46 days late)
% Done:

90%

Estimated time:
14:00 h
Spent time:

Add

Subtasks


Add

Related issues

Actions #1

Updated by Teja Sriram Sangani about 2 months ago

  • Status changed from New to In Progress
  • % Done changed from 10 to 70
Actions #2

Updated by Teja Sriram Sangani about 2 months ago

  • % Done changed from 70 to 80
Actions #3

Updated by Teja Sriram Sangani about 2 months ago

  • Due date changed from 10/22/2025 to 10/24/2025
  • % Done changed from 80 to 90